Google
Kingston Concerned About the LVEC
Currently known as the "KROCK Centre"
Formerly the "Kingston Regional Sports and Entertainment Centre" or KRSEC
Formerly the "Large Venue Entertainment Centre" or LVEC
Home   News
Whig Standard Feb 17 2007

‘Spend at the beginning, save at the end’

Ian Elliot
Local News - Saturday, February 17, 2007 Updated @ 11:13:56 PM

By Ian Elliot

Whig-Standard Staff Writer

Cost overruns at the city’s new downtown arena are the result of poor planning and communication, say municipal and construction experts.

But they go on to say there should no such thing as an unforeseen expense in such a project.

Council was told this week that the budget for the new arena has to increase by $4.3 million, raising the cost of the new facility to about $46.1 million. A motion on Tuesday’s agenda suggests cancelling the project, though work has been underway since the fall.

Politicians were told last week that the cost of outfitting the concession and sports cafe and buying furniture will cost more than $2.5 million and that a further $800,000 will have to be spent on the construction of the building, including upgrading the refrigeration system and installing cabling.

The cleanup of the site was also over budget and that, plus adding additional handicapped parking, will run $1.3 million more than budgeted.

Experts in the field who were interviewed by the Whig – and who had no direct ties to or interests in the project – say the costs may have been unanticipated, but ought to have been.

“Before you do anything, you have to ensure that everything is covered,” said engineer Jonathan Huggett, who has been a consultant on dozens of municipal arena projects, including those in Victoria, B.C. and Oshawa.

“Arenas are not difficult to build, and what we call F, F and E – which is fit, finish and equipment and includes things like appliances for the kitchen and furniture – is not difficult to estimate,” Huggett said.

George Cuff, a municipal governance expert who now works as a consultant for municipalities, said planning prevents surprises.

“There’s no fallback for administration to say we didn’t know, or we couldn’t have anticipated this, not with the amount of information that’s out there and the experience that other municipalities have had with these projects,” he said.

“Anytime these issues have come up for me, the question is, what did we do at the start that led to them? What caused this to go off the rails that we could have foreseen?”

Nick Smither, the president of

Municipal World, the trade magazine for Ontario’s municipalities, said cities need to have someone accountable for the project – for good and bad.



And because the average city manager isn’t an expert in outfitting a commercial kitchen, for example, they need to work with their own experts to make sure the details are right when companies bid on the work.

“If you spend the money at the beginning, you’ll save money at the end,” he said.

And Bob Hunter, the executive vice-president of Maple Leafs Sport and Entertainment, which has built arenas and other facilities across the country, speculated there might have been an assumption in an early draft that a private-sector operator would pay to equip the kitchen of a restaurant in exchange for a lower rent, and it was never corrected as the plan evolved.

“It would be difficult to attract a company to do that in a market such as Kingston because you just don’t have the volume of food there,” he said.

But he also said planning and reliance on the experience of those in the field at the start of a project was one of the most crucial elements and the key to realistic budgeting.

“When you’re building a budget, the one thing I would recommend is that you build yourself in lots and lots of contingency,” he said.

One of the most significant new reports to surface this week was a report by KPMG on the city’s process.

It highlighted a number of points of concern, and although it was given to the city nearly five months ago, had never been shared with either the public or council.

It found communication was poor and top city managers responsible for the project missed key meetings. It also suggested input from Arcturus, the company that will operate the facility and whose expertise, experts say, should have guided the city, wasn’t being acted upon rapidly.

The report, which has been in city hands since Sept. 22, 2006, predicted the costs of the project would rise based on the shortcomings.

“[The] current budget is incomplete – for example, environmental remediation,” it stated. “Without sufficient analysis, the opening budget and possible deviations may not be known early enough to mitigate any negative impacts on the overall cost.”

In December, the city discovered more water than it expected on the site and clearing it away cost $500,000 more than expected.

KPMG noted that the risk management plan was incomplete and that “major risks may be unknown and may not be implemented as a result of a lack of process to communicate and monitor risk and related actions.”

The consultants also observed there has not been one person accountable for the project from the start.

They note Don Gedge was original project manager but left the project following what the city describes as health problems. The new project manager, Lanie Hurdle, is new to the city and at the time the report was written was not assigned solely to the project (she has since been.)

City staff insist they have made major changes to how the project is run since receiving the report. They did a review of the budget with the companies involved in December and January, and hired a company to act as an owner’s representative in October.

But, Huggett said, faced with evidence that there were flaws in the starting process that will only magnify with time, the city needs to do an emergency audit .

“What you have got to do now is call a fast audit,” he said. “You need to get everyone in a room over a couple of days and get a checklist and go over every single item that is required to ensure it’s there and that it’s costed.”

KPMG also recommended a third-party assessment of the project design and budget.

The report also found that there was “very little public communication” about the progress of the project.

Alex Zetlin is a public relations and crisis management expert in New York City, whose Zetlin Strategic Communications firm works with governments on such huge and often controversial projects such as the rehabilitation of the Williamsburg and Manhattan bridges.

She said that aside from overseeing the engineering and construction work, cities have to keep citizens informed on a project’s progress – particularly when it involves large outlays of public money.

She also advised that if problems develop, the city needs to make them public and say what’s being done about them.

“If you have a problem, people are going to find out about it,” said Zetlin, whose firm advises governments to anticipate problems and get their information out first.

“And what we find is that if you’ve been communicating from the beginning, the backlash is less [when something goes wrong.]”

There are already mutterings in the city that the project cost was lowballed in the beginning and the overruns are actually costs that should have been included.

“I know that’s a pretty common citizen’s complaint, but I’ve seldom found that to be true,” he said. “I have some degree of sympathy for city staff in a situation like this, but we do expect first-rate advice from them.”

The consultants also noted there was a large degree of employee burnout among staff and “signs of excessive stress” among those they interviewed.

That came as no surprise to Smither, who noted staff had a city to run and putting a huge project on top of that – and in Kingston’s case, a number of them – could be too much.

“This type of thing is a fairly common problem because municipalities are overworked,” he said. “That’s largely the result of downloading – staff are responsible for a whole lot of things they weren’t doing before.”

But Huggett said no one has stopped an arena project that was underway, particularly in view of the tens of millions of dollars in penalties and other costs a municipality would incur.

“When you’re building an arena, once you’re in, you’re in.”

ielliot@thewhig.com